Request for Qualifications
Professional Engineering Services for the Rehabilitation of the Lake Asbury Dam Complex

Lake Asbury Municipal Service Benefit District (LAMSBD)
Clay County, Florida
January 2025

RFQ #2025-01
Request for Qualifications
Professional Engineering Services for the Rehabilitation of the Lake Asbury Dam Complex
Lake Asbury Municipal Service Benefit District (LAMSBD)
Clay County, Florida
January 2025

1. PURPOSE

The LAMSBD (or “Board”) intends to select one or more professional engineering design firm (or “Engineer”) to provide surveying, inspection, geotechnical exploration & testing, design, permitting, bidding and construction phase services for any sub-project associated with the Lake Asbury Dam and Spillway Rehabilitation Project (HEREIN CALLED “THE PROJECT”). Firms submitting qualifications for the project shall be registered with the Florida Board of Professional Engineers, be qualified by a Professional Engineer licensed in Florida, and recognized as a legitimate and reputable dam design consulting entity with the Florida State Dam Safety Office; Division of Water Resource Management.

2. BACKGROUND:

The LAMSBD system consists of 3 interconnected lakes known as Lake Asbury, South Lake Asbury and Lake Ryan with associated dams and spillways. Lake LARC, owned and operated by a separate entity, drains into this system of lakes. South Lake Asbury, Lake Ryan, and Lake LARC discharge into Lake Asbury. Lake Asbury discharges into Black Creek. A vicinity map showing the location of each lake and the associated dam is provided in Figure 1.

The dams and associated drawdown structures were constructed in 1965, creating lakes which added to the retail value of the residential land development (USACE, 1978). These are earthen dams with a clay core. The drawdown structures for each lake are made of corrugated metal pipes. The emergency spillway for the Lake Asbury Dam is a triple concrete box culvert, and the emergency spillway for the South Lake Asbury Dam is a double culvert made of aluminum with segmented block headwall (Jackson, 2020). Approximately 25 years after construction, the corrugated metal pipes began to degrade and were lined with High Density Polyethylene pipes. Grout was pumped between the corrugated metal pipe and the new HDPE liner. Improvements were made to the South Lake Asbury Dam in approximately 2013, which included the addition of the existing emergency spillway.

Lake Asbury Dam discharges into Black Creek via two primary spillways (referred to in this report as drawdown structures) and an emergency spillway. South Lake Asbury discharges into Lake Asbury via one primary spillway and an emergency spillway. Both Lake Ryan and Lake LARC discharge into Lake Asbury via one primary spillway.

The primary drawdown structures (primary spillway) in each lake are used to maintain water level in the lakes at the normal pool elevation and are used to drawdown the lakes below the normal pool elevation in anticipation of a large storm event such as a hurricane. The emergency spillway in the Lake Asbury Dam and the South Lake Asbury Dam discharge when the lakes are above the normal pool elevation. Portions of the Primary and Emergency Spillways for the Lake Asbury Dam are located on property not owned by LAMSBD.

FIGURE 1 - Vicinity map

The design of the drawdown structures for each dam are similar. A schematic depicting the dam and associated drawdown structures and emergency spillway (cross section) is provided in Figure 2. The basin area associated with each dam is depicted in Figure 3.

The combination of the primary culvert (A) and the riser pipe (O) with kettle/trash rack (P) maintain the normal pool elevation in each lake. Water enters through the riser pipe at the surface of the lake and flows to the downstream discharge point via the primary culvert. The trash rack is also commonly called the Kettle. The combination of the primary culvert (A), the riser pipe (O) with trash rack (P) and the drawdown culvert (B) are utilized to pull water below the surface of the lake near the base of the dam to the downstream discharge point. Water enters the drawdown culvert (B) near the base of the dam and directs it to the primary culvert where it ultimately discharges to the downstream receiving water body. A valve, in the drawdown culvert near the base of the riser pipe, controls when the drawdown pipe is opened or closed. When it is open it allows water to flow through the drawdown culvert to the primary culvert and onto the downstream discharge point. When the valve is closed water can only move from the lake to the downstream discharge point via the riser pipe and primary culvert. The operation of the valve is key to the successful use of the drawdown structures.

For the Lake Asbury Dam and the South Lake Asbury Dam, when the lake is above the normal pool elevation (normal lake stage) and it reaches above the crest of the emergency spillway, lake water will discharge through the emergency spillway to the downstream discharge point. For the Lake Asbury Dam water flowing through the emergency spillway will discharge into a concrete flume on the downstream side of the dam. For the South Lake Asbury Dam water flowing through the emergency spillway flows over Articulating Concrete Block (ACB) surface to the discharge point into Lake Asbury.

The Lake Asbury, South Lake Asbury, Lake Ryan, and Lake LARC dams have a Hazard Potential of High by the National Inventory of Dams which is maintained by the US Army Corps of Engineers. The last update for these dams appears to be August 3, 2018. A dam with a high hazard potential classification means that loss of human life is likely if the dam fails. The information can be found at https://nid.sec.usace.army.mil.

Various studies and reports have been conducted recently and in the past regarding the history and conditions of the dams. Detailed descriptions of the history and design of the dams considered in this report can be obtained from several of these reports listed in the Reference Section of this report.

FIGURE 2 - Description and Depiction of Existing Conditions of Dams

FIGURE 2. Description and Depiction of Existing Conditions of Dams

FIGURE 3. Basin Map – The boundary of the drainage basin for each lake.

FIGURE 3. Basin Map – The boundary of the drainage basin for each lake.

3. SCOPE OF SERVICES

The scope of services includes field investigations, surveying, geotechnical investigations, preliminary design and detailed design, permitting, bidding and construction services for the project. Detailed work tasks are as outlined in this section. Unknown issues and needed work to the Lake Asbury Dam Complex may be discovered as the project continues and, therefore, the scope of services may also include any additional issues and needed work later identified but not currently known. Suggested modifications to the scope shall be detailed in the Engineer’s proposal. The Engineer shall provide all necessary services required for a complete permitted design package suitable for bidding and construction of the project. Sub-projects and completion dates will be assigned based on availability of funds.

Task 1 – Project Administration, Management, and Quality Control

Throughout all tasks, the Engineer shall provide project administration and management activities such as staffing, sub-consultant coordination, budget management, schedule management, and coordination with the LAMSBD Board and maintain the quality of the work products defined within this scope as consistent with applicable standards and expectations.

Project administration and management includes general internal project management based on the tasks in this Scope of Work throughout the life of the project. Engineer shall provide the following:

• Prepare for and attend project kick off meeting.

• Prepare a Project Management Plan with team member contacts, stakeholder contacts, schedule, fee/budget and sample invoice.

• Prepare a Risk Register identifying potential risks for the project and associated mitigation strategies.

• Prepare and submit monthly status reports including an updated project schedule, current status of the project tasks and project financials.

• Schedule and attend monthly progress meetings with the Board Chair, as needed, during design and construction.

• Attend monthly LAMSBD Board meetings, as needed, to present the current status of the Project and address questions.

• Provide meeting summaries for all Progress Meetings, design review meetings, permitting meetings, State Agency meetings or other meetings.

• For each deliverable review, provide review comment spreadsheet for all stakeholder review comments including Engineer response and action on each review comment.

• Perform quality assurance and quality control (QA/QC) reviews for the Project.

• Coordinate and manage subcontractor(s) as applicable.

Task 2. Field Surveys, Investigations, and Preliminary Design

A detailed field survey shall be conducted for any sub-project being designed for THE PROJECT. The engineer shall provide a due diligence review and associated presentation to the Board of Trustees regarding the ability to obtain permits and financial feasibility of preliminary design options.

• Engineer shall provide planimetric and topographic survey work and create a topographic base file for use in the project design, permitting, and construction document preparation.

• Geotechnical and structural investigations will be completed for the dam – Engineer shall conduct complete investigations for the dams, spillways, and drawdown structures using to the extent possible all of the historical inspection work completed by others.

• Engineer will provide a brief Technical Memorandum (TM) summarizing the results of the field reconnaissance and other preliminary considerations for review and approval by the LAMSBD Board.

• Engineer will provide at least two viable design options for consideration by the Board of Trustees.

• Engineer will provide a written record of conversations with SJRWMD permit reviewers to assure the Board of Trustees that the proposed design can meet current permit review requirements.

Task 3. Design Document Preparation

The detailed design phase will consist of the preparation of drawings and specifications for permitting and construction of the any sub-project.

All design documents shall be prepared in accordance with standard engineering practice and State of Florida requirements.

The design will be conducted in the following phases. Engineer will provide two (2) sets of full-size drawings and PDFs for review and coordinate and conduct a workshop meeting at the 30%, 60% and 90% design milestones to review the design documents with the Board.

The 30% Preliminary Engineering design will consist at a minimum of the following:

• Base drawings utilizing field survey data

• Preliminary Plans indicating the proposed horizontal alignment

• Locations of tie ins and connections

• Preliminary opinion of probable construction cost

• Standard Construction Details

• Updated permitting requirements based on field delineation and survey results

The 60% design shall address comments received at the 30% phase and consist at a minimum of the following:

• Drawings including dam, spillway, and drawdown structure plan and profile sheets

• Valving and connection piping details

• Sizing / locational analysis for air release and surge relief valves

• Erosion and sedimentation control plan and details

• Technical specifications

• Updated opinion of probable construction cost

The 90% design shall address comments received at the 60% phase and consist of a full set of plans, details, specifications and bid documents. It is anticipated 60% drawings will be sufficient for project permitting.

The 100% design shall include the resolution of all review comments and incorporation of regulatory agency comments. The design documents shall be sufficient for bidding the project for construction.

Task 4. Permitting

In preparation for bidding and construction of the project, Engineer will prepare and coordinate submittals, address comments and obtain all requisite permits including but not limited to:

• Maintain full compliance with Florida Dam Safety and SJRWMD protocols

•Compliance with Corps of Engineers 404 Permit and all required actions and submittals

• Florida Environmental Resource Permitting

Task 5. –Bid Phase Assistance

When approved by LAMSBD Board, the Engineer will assist in the bidding process for construction of the project. Engineer will prepare a complete set of contract documents, including:

• Project technical specifications

• Project bid drawings including incorporation of all applicable permit review comments

• Project Bid Forms

• Project Front End Documents per EJCDC® Construction Contract Document standards

During the bidding process the Consultant will:

• Maintain plan holders list

• Issue bid documents (plans and specification packages)

• Attend a Pre-Bid Conference and assist Board in conducting the conference

• If necessary, prepare addenda to interpret, clarify, and amend the Contract Documents

• Answer technical questions from contractors during the bidding period

• Attend the bid opening in collaboration with the Board.

• Tabulate the bids, review contractor references and perform due diligence review in coordination with the Board.

• Upon Contractor Selection, prepare 6 sets of Contract Documents

Task 6 –Stakeholder Involvement and Public Outreach

Engineer will be expected to support to LAMSBD as it relates to stakeholder involvement and public outreach, including the participation of up to three public meetings and providing one GIS based project overview exhibit and detailed technical drawings. The Board will develop mailing lists and maintain community contacts for all stakeholders for use during the public awareness campaign.

Task 7 – Construction Phase Services

Engineer will provide construction observation and administrative services during the construction period of the project. The Board will prepare a Notice of Award to the selected contractor and prepare and issue a Notice to Proceed. The Engineer will provide additional administrative services during construction that will include the following items:

• Attend and assist in conducting a pre-construction conference

• Review submittals and shop drawings; produce submittal log

• Review Requests for Information; produce RFI log

• Review Periodic Requests for Partial Payments to the Contractor

• Review Change Order Requests, produce change management log

• Attend monthly progress meetings; produce agenda and minutes

• Provide contract close-out assistance (punch list support, etc.)

• Coordinate periodic onsite meetings with Board and Agency personnel as required

• Assist in the selection of an independent geotechnical testing laboratory to perform Quality Control testing. LAMSBD to compensate sele ted testing lab for services. Engineer to review and approve testing methods, equipment, and results.

• Provide full time construction inspection and quality control

• Prepare record drawings based on the contractor’s redline markup drawings, contractor’s survey information

• Record drawings will be submitted by Engineer in AutoCAD, PDF and GIS formats.

ESTIMATED RFQ SCHEDULE:

RFQ Advertised January 30, 2025
RFQ Due Date February 28, 2025
Selection Ranking March 3, 2025
Oral Presentations (Optional) March 17, 2025
Final Selection April 7, 2025
Negotiation of Fee Structure April 14, 2025
Execution of Contract(s) May 5, 2025

4. SUBMITTAL DEADLINE AND DELIVERY

A. Eight hard copies and electronic copies on two USB drives of the Proposal must be received by LAMSBD no later than 4:00 P.M. on Friday, February 28, 2025.

B. The Project name and Firm’s name and address must be shown on the outside of the sealed envelopes, addressed to, and delivered to:

The Law Offices of Cobb & Gonzalez, P.A.
4655 Salisbury Rd., Suite 200, Jacksonville, FL 32256

C. No submittals will be accepted after the deadline. Submittals received after the designated time will not be considered.

D. Submittals must be paper copies, appropriately bound. Emailed or faxed copies will not be accepted.

E. This is a Qualifications Based Selection (QBS) procedure for Professional Engineering Services, and there will be no public opening of the Proposals.

F. Firms intending to submit Statements of Qualifications should register their intent by contacting Mike Clemons, Chairman, at mike.clemons@lamsbd.com. The purpose of this registration is to ensure that interested firms are promptly notified of any addenda that might arise.

5. PROPOSAL CONTENTS
Proposals should be bound with the name of the firm and name of the Project visible on the outside cover. Each submittal will be limited to forty (40) double-sided sheets addressing all aspects of the Request for Qualifications.
To standardize responses and simplify the comparison and evaluation of responses, all submittals must be organized in the manner set forth below. The document should have a Cover Letter, Table of Contents with the following major sections, including tabs marking section locations. Sheets should be printed double-sided (20 pages, exclusive of Table of Contents, Resumes and tabs):

A. General Information

1. A cover letter signed by an officer of the firm.

2. Provide a primary contact point for all correspondence related to the proposal including name, title, phone number, and email address.

3. Provide the name, resume, office location, and Florida Board of Professional Engineers License number of the Engineer of Record for any sub-project.

4. Provide Certificate of Insurance (ACCORD format preferred), including dollar limits, currently held by the firm. The Board may require additional insurance related to agreements/contracts arising from this RFP. All insurance carriers must be A rated. LAMSBD must be listed as an additional insured on all policies. These will be discussed with the firm at the time of contract/agreement negotiation.

Required Minimum Coverages:

A. Workers’ Compensation Florida Schedule Minimums

$100,000 – each accident
Statutory Coverage and Employer’s $100,000 – each employee
Liability – $500,000 – policy limit for disease

B. Comprehensive General Liability

$1,000,000 – bodily injury each occurrence
$1,000,000 – bodily injury aggregate
$1,000,000 – property damage each occurrence
$1,000,000 – property damage aggregate

C. Products – Completed Operations $1,000,000 – aggregate

D. Business Auto Liability (same as Comprehensive General Liability; all autos)

E. Professional Liability ($2,000,000)

F. Excess or Umbrella Liability (Optional)

5. A statement agreeing to all terms contained in the Request for Qualifications document including permission for LAMSBD and its representatives to contact references, clients, contractors or others to seek information about the firm’s past performance, as well as permission for those persons contacted and its representatives to provide requested information.

6. A statement that the firm currently has in-house resources to perform all work required for each of the Project parts except in those specialized areas that are clearly listed in the submittal. Provide an organization chart showing key personnel.

7. A statement by the firm certifying that, in accordance with Chapter 287.133 and to the best of its knowledge, there are no circumstances that would cause a conflict of interest on the part of the firm or its proposed sub-consultants or sub- contractors in performing services for LAMSBD, and that no company or person other than bona fide employees working solely for the Consultant has been employed or retained to solicit or secure the proposed contract, and that the firm has not had their right revoked to conduct transactions with public entities in the State of Florida.

8. Describe respondent’s firm by providing its full legal name, date of establishment, type of entity, short history, current ownership structure, and any recent or materially significant proposed change in ownership.

9. Identify any litigation, arbitration, or mediation claims that involved similar projects. Identify any contract or subcontract held by the firm or officers of the firm, which have been terminated. Include only those actions involving projects completed during the past 10 years. Include claims that were initiated by or against the project Owner and the Engineer under contract with the project Owner. Briefly state the nature of the claim and the outcome.

B. Firm’s Experience and Performance on Similar Projects (25 points)

Submit the following information on past projects to illustrate the specialized expertise, demonstrated experience, applicable qualifications, and available resources of the firm with emphasis on key team members proposed for this project. The responding firm shall provide a summary of up to five (5) similar projects of similar size and nature within the last 10 years and the following information:

1. For each listed sub-project, provide the following:

a) Project name, location, description, and status of the project.

b) Project’s original contracted engineering cost and final engineering cost. Explain any difference.

c) Project’s construction cost.

2. Contact information (reference name, title, email address and phone number) for Owner for each project.

3. Key project team members serving on each of the above listed projects with emphasis on the participation of team members proposed for this Project. Specialized expertise and/or resources applied during project, with concise explanations of their value and relevance to this Project.

4. Describe any issues relevant in evaluating the ability of the responding firm to handle the proposed Project.

C. Project Team Qualifications (25 points)

Submit proposed Project team information to include the following:

1. Organizational chart showing key personnel who will be assigned to the Project; include the name and role/responsibility of each key team member. Include only those staff members who will commit a substantial percentage of their time to the work. List the approximate number of technical staff that is expected to serve in support roles on the Project. Show reporting structure of the Project team including any sub-consultants. Include a listing of work elements that will be performed by sub-consultants and state the names of proposed sub-consultants.

2. For each key person identified, list their length of time with the firm and at least two comparable projects in which they have played a primary role. If a project selected for a key person is the same as one selected for the firm in Section B, provide just the project name and the role of the key person. For other projects provide the following:

a) Description of project

b) Role of the person

c) Project’s original contracted engineering cost and final cost.

d) Project owner.

e) Reference information (two current names with telephone numbers and email per project).

D. Understanding the project and approach to performing the required services (20 points)

1.Provide a discussion of your project understanding and approach, with emphasis on modifications, deviations, or improvements to the proposed scope of services.

2.Discuss the major issues and / or risks your team has identified on this project and how you intend to address and mitigate those issues.

3.Describe your firm’s project management approach and team organization during the project. Describe systems used for planning, scheduling, project execution and quality control.

4.Provide a schedule by phase and task for completing the work.

5.Identify any assumptions and services anticipated to be provided by the LAMSBD Board.

6. Provide any additional information that you feel would assist the Board in making this project award decision.

E. Proximity to Project Site (5 points)

1.Location of the consultant’s home office (corporate headquarters) and location of the office where the project work will be performed will be a factor in selection. Deference will be given to firms with office locations and the project manager located in the Northeast Florida region.

F. Interview (25 points)

An interview (optional) will be held among short-listed firms at a time and date selected by the LAMSBD Board. Information will be provided at a later date.

6. QUESTIONS AND CLARIFICATIONS

Any questions concerning this Request for Qualifications should be directed to the person listed below. No interpretation or clarification of the meaning of the instructions or scope of services will be made orally except for general information that does not require a clarification. Every request for such interpretation should be in writing, submitted by email and addressed to the individual shown below. To be given consideration, questions must be received at least fourteen (14) calendar days prior to the date fixed for the opening of qualifications.

All clarifications and any supplemental instructions will be posted on the LAMSBD website at the following address: https://www.lamsbd.com

Please check the website periodically for updates to the Request for Qualifications. It is incumbent upon the responding firms to review LAMSBD’s website for any updates or addendums to the RFQ on an ongoing basis.

Address questions to:

Mr. Mike Clemons, LAMSBD Chairman
Email: mike.clemons@lamsbd.com

7. EVALUATION AND SELECTION

Submittals from each Firm will be evaluated on the basis of the information submitted, along with an analysis of other available information. The Board may conduct investigations or interviews, as it deems necessary, to assist in the evaluation of the qualifications submitted. A selection committee will review the proposals and rank the Firms and will award points to each category listed in Section 6 in accordance to completeness/ responsiveness of each category. The initial evaluation is based on a total maximum score of 100 points (Items A- E). Maximum points for each category are included in Section 6.

After the initial evaluation, the Board will develop a “short-list” of the top three or four firms or teams. These “short-listed” firms will be interviewed, at a mutually acceptable date. A final score based upon Items A-F will be the basis of a final selection.

It is anticipated a contract for engineering services will be entered into with the firm that, in the opinion of the Board, offers the most favorable combination of qualifications, and approach. A budget will be negotiated with the selected firm upon notice of award. In the event LAMSBD is unable to negotiate a mutually agreeable cost with the number one ranked firm, LAMSBD is authorized to begin negotiations with the number two ranked firm. The Board reserves the right to decline awarding the contract depending upon qualifications and final proposals.

8. CONTRACT

The successful respondent will be expected to enter into an Agreement with LAMSBD as the lead agency. The contract will be based upon the EJCDC® E-500, Agreement Between Owner and Engineer for Professional Services.

9. OWNERSHIP OF SUBMITTAL DOCUMENTS

Upon receipt of the submittal by the LAMSBD Board, the submittal and all included documentation shall become the property of the Board, without compensation to the respondent, for disposition or usage at its discretion. The Board assumes no responsibility or obligation to respondent Firms and will make no payment for any costs associated with the preparation or submission of submittals. All work, including but not limited to planning, programming, cost estimates and summaries, plans, specifications, concepts, ideas, and other materials prepared by or for the respondent firm for the Board under this Request for Qualifications and any subsequent proposal shall become the property of the LAMSBD Board. However, such provisions do not include the publication, distribution, or sale of such submittals to third parties not employed by or under contract to the Board.

REFERENCES

USACE, 1978; US Army Corps of Engineering (USACE), Phase 1 – Inspection Report, National Dam Safety Program Report, dated July 1978, was written for the Lake Asbury Dam, the South Lake Asbury Dam, and the Lake Ryan Dam. Three reports were produced, one for each dam. The reports were prepared as part of the National Dam Safety Inspection Program authorized by the United States Congress in August 1972.

LAW, 1988; LAW Engineering, Report of Engineering Study, Lake Asbury Dams, Safe Compliant Status Evaluation, December 1988, prepared for LAMSBD.

RS&H, 2000; Reynolds, Smith & Hills, Inc., Lake Asbury Drainage Sector Study, November 2000, prepared for Clay County Board of County Commissioners.

MACTEC, 2004; MACTEC Engineering and Consulting, Inc., Report of Geotechnical Observations, Lake Asbury Dams, Green Cove Springs, FL., dated June 2004.

Jackson, 2020; Jackson Geotechnical Engineering, LLC, Report of Dam Assessment Lake Asbury, South Lake Asbury, and Lake Ryan, dated September 14, 2020, prepared for LAMSBD.